Replace 4L Glide Slope Shelter04/27/2015 - 07/18/2015
Project InitiativeDescriptionStatus StartFinish
Construction Replace 4L Glide Slope Shelter After Hurricane Sandy, flood plane elevations were revised, and funding provided to raise equipment shelters. In order to minimize outage times, this replacement will be completed during Stage 3 of the PANYNJ 4L-22R Refurbishment project. Shelter is on site, installation planned to occur in June. 04/27/2015 A 07/18/2015
A = Actual Date

This action plan is intended to establish a climate of accountability for the FAA, airports, and airlines. No project will be implemented prior to the completion of all required analysis, reviews and approvals. The information provided is for planning purposes only. For actual Runway and Taxiway Closures, and Equipment Outages, please review current Notices to Airmen (NOTAMs).