LGA - LaGuardia Airport

Data Last Posted: 07/06/2015 - 11:16 AM
LGA Airport Diagram

LGA - LaGuardia Airport (Projects)
ProjectStartFinish
2015
2016
2017
2018
2019
Terminal Flight Data Mgmt (TFDM) for LGA 01/01/2022 12/31/2022
Starts in 2015Begin: 01/01/2022, Finish: 12/31/2022Ends after 2019
Digital Non-voice Communications (DataComm), LGA 03/19/2010 A 03/14/2016
Starts Prior to 2015Begin: 03/19/2010, Finish: 03/14/2016Ends in 2016
Establish Runway Status Lights (RWSL) 12/30/2008 A 04/15/2015 A
Starts Prior to 2015Begin: 12/30/2008, Finish: 04/15/2015Ends in 2015
A = Actual Date

This action plan is intended to establish a climate of accountability for the FAA, airports, and airlines. No project will be implemented prior to the completion of all required analysis, reviews and approvals. The information provided is for planning purposes only. For actual Runway and Taxiway Closures, and Equipment Outages, please review current Notices to Airmen (NOTAMs).