Schedule
| Segment 1 | |||
|---|---|---|---|
| Milestone | Projected Completion Date |
Key site SAT Successful Completion |
Status |
| Contract Award | August 2007 |
Complete |
|
| NPRM Issued | October 2007 |
Issued; displayed on Federal Register 10/2/07 |
|
| Integrated Baseline Review | October 2007 |
Complete |
|
| Preliminary Design Review (PDR) | November 2007 |
Complete |
|
| Critical Design Review (CDR) | February 2008 |
Complete |
|
| Key Site Initial Operating Capability (IOC) of Broadcast Services | August 2008 |
May 2008 |
|
| In-Service Decision (ISD) of Broadcast Services | November 2008 |
||
| Gulf of Mexico Comm. and Weather IOC | September 2009 |
March 2009 |
|
| Louisville IOC of Surveillance and Broadcast Services | October 2009 |
April 2009 |
|
| Final Rule Published | November 2009 |
||
| Gulf of Mexico IOC of Surveillance and Broadcast Services | December 2009 |
June 2009 |
|
| Philadelphia IOC of Surveillance and Broadcast Services | February 2010 |
August 2009 |
|
| Juneau IOC of Surveillance and Broadcast Services | April 2010 |
October 2009 |
|
| Surveillance and Broadcast Services ISD for ADS-B | September 2010 |
||
For essential services, SAT occurs 3 months prior to IOC. For critical services, SAT occurs 6 months prior to IOC. Key site SATs are considered default milestones.
| Segment 2 (2009 – 2014) | |
|---|---|
| Milestone | Projected Dates |
| Implementation: | |
| Continue Initial Aircraft to Aircraft Application Deployment | FY 2010 – FY 2014 |
| Future Aircraft to Aircraft Requirements Definition / Deployment | FY 2010 – FY 2014 |
| Continue / Complete TIS-B / FIS-B Deployment | FY 2009 – FY 2012 |
| Continue / Complete ADS-B NAS Wide Infrastructure Deployment | FY 2010 – FY 2013 |
| Complete 26% Avionics | FY 2014 |
| Lifecycle: | |
| Targeted Removal of Legacy Surveillance | FY 2016 – FY 2020 |
| Complete 100% Avionics | FY 2020 |
| Complete Removal of Targeted Legacy Surveillance | FY 2023 |
| Complete Targeted Removal of TIS-B | FY 2025 |