Workplan - Plenary

Plenary
Completed Plenary #1 - Washington, D.C.
  • Agree Terms of Reference
  • Define Organizational Structure
  • Define Milestone Plan
  • Stand-Up Phase 1 & Phase 2 SPR Working Groups
5-7 JUN 2007
Completed Plenary #2 - Europe
  • Draft Preliminary Review
  • Stand-Up Interoperability Working Group
  • Review and Revise Issue Baseline
  • Harmonize with EUROCAE
2-4 OCT 2007
Completed Plenary #3 - U.S. Scottsdale, AZ
  • Environment & Service Definitions
11-15 FEB 2008
Completed Plenary #4 - Europe Paris, France
  • WP 1 OSA
16-20 JUN 2008
Completed Plenary #5 - U.S. Washington, D.C.
  • WP1 SPR & WP1 Interop
22-26 SEP 2008
Completed Plenary #6 - Europe Toulouse, France
  • FRAC updates
8-12 DEC 2008
Completed Plenary #7 - U.S. Scottsdale, AZ
  • WP2 OSD & FIS+ADS PM
30 Mar - 3 Apr 2009
Completed Plenary #8 - Europe Toulouse, France
  • WP1 and WP2 with SPR and Interop
21-25 SEPT 2009
Completed Plenary #9 - U.S. Albuquerque, NM.
  • WP1 and WP2 with SPR and Interop
14-18 DEC 2009
Completed Plenary #10 - Europe Mallorca, Spain
3-7 MAY 2010

Workplan - ALL Sub Groups

ALL Sub Groups
CompletedBrussels, Belgium 22-24 JAN 2008
CompletedWashington, D.C. 11-13 MAR 2008
CompletedBrussels, Belgium 22-24 APR 2008
CompletedWashington, DC MAY 13-15 2008
CompletedWashington, DC 22-24 JUL 2008
CompletedMunich, Germany (SG-2 and SG-3) 26-28 AUG 2008
CompletedMelbourne, FL 20-24 OCT 2008
CompletedBrussels, Belgium 10-14 NOV 2008
CompletedMaastricht Netherlands 8-12 JUNE 2009
CompletedAtlantic City, NJ 7-9 JULY 2009
CompletedLangen, Germany 24-28 AUG 2009
CompletedSeattle, WA 26-30 OCT 2009
CompletedLangen, Germany 1-5 MARCH 2010

Review Timeline

  • Time to develop 1st draft (60 Days) Plenary
  • Time to incorporate comments on 1st draft and develop Final Draft Plenary
  • Time to incorporate comments on Final Draft and Develop Preliminary Final Document Plenary
  • Time to incorporate comments on Preliminary Final Document
  • Documents available 60 dats prior to start of plenary
  • Comments due 30 days prior to start of plenary

Detailed Review Timeline (Time in Calendar Days)

  • Preliminary Draft Review
    • Produce Review Material (60 Days)
    • Committee Review (30 Days)
    • Disposition and Incorporate Comments (3 Weeks)
    • Distribute For Plenary Review (1 Week)
  • All other Reviews
    • Produce review material (45 Days)
    • Build Document (5 Days)
    • Committee Review (30 Days)
    • Disposition and Incorporate Comments (3 Weeks)
    • Distribute for Plenary Review (1 Week)

Plan Definitions

  • Annotated Outline: Complete document outline with brief description of the contents, focused traceability to relevant reference documents, of each labeled section, table, and figure. Sufficient detail to assess completeness and support labor estimation.
  • Draft Document: Complete text. Tables figures may be notional. May include TBDs.
  • Final Document: Complete text, tables and figures. All TBDs resolved.