Section
22. Contingency
Plan Support
System (CPSS)
17-22-1. PURPOSE
This section
prescribes
policies and
guidelines for
managing ARTCC
Operational
Contingency Plan (OCP)
data within the
Contingency Plan
Support System (CPSS).
The CPSS is
maintained via the
RMT.
17-22-2. DEFINITION
The CPSS, as
defined in FAA
Order JO 1900.47,
Air Traffic
Organization
Operational
Contingency Plan,
is a software
application used
to collect, share,
publish, and
distribute OCPs
for operational
access and use by
field facilities,
the ATCSCC, and
customers during
ATC Zero events.
17-22-3. RESPONSIBILITIES
a. The
ATCSCC must:
1. Manage
the CPSS database
following FAA
Order JO 1900.47,
Air Traffic
Organization
Operational
Contingency Plan.
2. Designate
a POC for the
management of the
CPSS database.
b. ARTCCs
must:
1. Develop
and maintain the
accuracy of OCP
data within CPSS
following FAA
Order JO 1900.47,
Air Traffic
Organization
Operational
Contingency Plan.
2. Designate
a POC to
coordinate with
the ATCSCC on the
management of the
ARTCC's CPSS
database
information.
3. Coordinate
with all affected
facilities when
changing CPSS data
before including
them in the CPSS
database.
4. Ensure
that CPSS data are
available to
operational
positions.
NOTE-
Before publication
in the CPSS, the
facility must
ensure that
hardcopy, or other
electronic means
of making this
information
available, is
provided to
operational
personnel and the
ATCSCC.
5. Tell all
affected offices
when making any
change to the
National Airspace
System that might
affect internal or
adjacent ARTCC
contingency plans
(for example,
airway changes,
frequency changes,
airspace redesign,
airway
realignment, etc.)
6. Report
unusable,
inaccurate, or
unsatisfactory
CPSS information
directly to the
ATCSCC CPSS POC.
Real-time
implementation
problems should be
reported to the
ATCSCC National
System Strategy
Team and to the
ATCSCC CPSS POC.
Reports must
include the
facility plan
name, affected
sectors, specific
description of the
impact, and if
appropriate,
suggestion for
modification.
7. Coordinate
with underlying
terminal
facilities for all
matters pertaining
to CPSS data
information.
c. Service
Center Operations
Support Group
must:
1. Review
CPSS data for
currency and
consistency.
2. Serve as
liaison between
ARTCCs and ATCSCC
on CPSS matters.
3. Serve as
information and
training resource
for ARTCCs to help
them maintain
current and
accurate
information in
CPSS.
17-22-4. PROCEDURES
a. OCP data
for each ARTCC
must be published
within CPSS via
the national RMT
database. Updates
to the RMT
database will
coincide with the
56-day chart
update cycle.
b. OCP data
must be processed
in accordance with
the following
timelines:
1. All
revisions to CPSS
data must be
provided to the
ATCSCC CPSS POC at
least 30 days
before each chart
date.
2. The
ATCSCC POC must
enter all
revisions to the
CPSS data at least
14 days before the
chart update. The
RMT database will
then be locked.
|