Metroplexes at a Glance
Metroplex Daily Average by Fiscal Year Projected Annual Benefits Metroplex Phase
2014 Total Operations 2014 Scheduled Flights Fuel Savings (Gallons of fuel in millions) Value of Fuel Savings (Fuel costs in millions) Carbon Savings (Metric tons of carbon in thousands)
Atlanta 3,097 2,329 2.2** $6.3 18.8 Implementation
Charlotte 2,636 2,026 3.3** $9.4 28.0 Implementation
Cleveland-Detroit 2,341 1,435 3.4* $9.7 28.9 Design
D.C. 2,760 2,001 2.1** $6.1 18.2 Complete
Denver 2,757 1,530 0.6* $1.8 5.4 Design
Houston 2,609 1,615 1.8*** $5.3 15.7 Complete
Las Vegas 2,044 859 2.6* $7.5 24.8 Pre-Design
North Texas 4,046 2,080 2.6** $7.5 22.4 Complete
Northern California 3,220 1,824 0.7** $2.0 5.6 Complete
Phoenix 1,796 1,049 1.4* $3.9 11.6 Paused
South Central Florida 6,735 2,602 5.4* $15.5 46.1 Design
Southern California 5,897 2,557 2.7* $7.8 23.3 Evaluation

Last Updated August 2016

* Indicates the source is derived from Study Team notional models;
** Indicates from Design Team;
*** Indicates that analysis was conducted based on Radar track data collected during the first few months of final implementation for that project