Event Scheduled/Planned
Date
Request for Information (RFI) Market Survey #10916 July 14, 2011
Acquisition Category (ACAT) Level 1, New Investment January 2015
Request for Information (RFI) Market Survey #19301 January 12, 2015
RFI Market Survey #23595 February 9, 2016
RFI Market Survey #25899 October 31, 2016
RFI Market Survey #25900 October 31, 2016
Request for Comments (RFC) 28321, Draft Screening Information Request (SIR) #1 September 25, 2017
Original FTI contract ends, FAA extends the contract on a single source basis for five more years (FY2018-FY2022) September 30, 2017
FAA Enterprise Network Services Program Industry Day April 25, 2018
RFI Market Survey #30397 June 4, 2018
RFC #30994, Draft SIR #2 July 31, 2018
RFC #31552, Draft SIR #2 – Release of Additional Sections October 4, 2018
RFC #34003, Draft SIR #3 Release June 30, 2019
RFI #34044, FENS Acquisition Document Library July 3, 2019
Final SIR Release to FAACO October 31, 2019
Receive Offerors Proposals January 9, 2020
FAA Enterprise Network Services Program Contract Award September 30, 2020