Q-U62. Can alternative project delivery methods be used for airside construction?
Yes. Section 723(a) of the FAA Reauthorization Act of 2024 (P.L. 118-63) amends 49 U.S.C. §47142 by revising the section heading to “Alternative Project Delivery” instead of “Design-Build Contracting” and expanding the allowable contract types from solely design-build to include progressive design-build and integrated project delivery methods, collectively referred to as “Covered Project Delivery Contracts.” See Q-U70. Refer to 2 CFR 200 and Appendix U of the AIP Handbook.