(Start: OMB Exhibit 300 Attachment 1 for the Investment Analysis Readiness Decision (IARD))
Review
- The CONOPs of the system.
- FAA FAST AMS Lifecycle Phases and Decisions guidance website:
- FAA FAST ISS Flow Chart of the CRD section
- Security engineering activities.
- The NAS-SR1000 security requirements section.
- To obtain the document please contact Linda Suppan (Acting Manager).
Coordinate
- Service Unit/Service Area Certification Team Lead to determine plans and strategy for SCAP activities including determining the level of effort and security activities.
- ATO Information System Security Manager (ISSM)
- ATO Designated Approving Authority (DAA), Information System Security Certifier (ISSC), and Information System Security Manager (ISSM)
- ATO Service Unit/Service Area Certification Team Lead
- ATO Service Unit/Service Area ISSO.
- The individual is responsible for all the security functions for the program and is designated by the Program Manager.
Generate
- “Developing CONOPS and Preliminary Security Requirements (b)”
- CONOPS of system.
- ISS section of the Preliminary Requirements. (pPR document).
- For assistance in developing security requirements contact Kenneth Kepchar, ATO-P ISS Chief Scientist System Engineer.
- The 800-53 controls.
Deliverable(s)
- OMB Exhibit 300, Attachment 1: Preliminary Program Requirements (pPR)
- ISS Section of the Preliminary requirements. (pPR)
End CRD for AMS decision point: #2 & AMS Phase Mission Analysis (MA)